TxDOT: Weekend road closures focus on rebuilding of interchange on Northwest Side

SAN ANTONIO (KTSA News) — Major closures will effect travel this weekend at the junction of Loop 1604 and Interstate-10.

As part of the Loop 1604 North Expansion project, TxDOT is scheduled to fully close the interchange of Loop 1604 and I-10 in northwest San Antonio for this weekend. These closures will allow the contractor to install steel beams as construction work begins to focus on building ramps and bridges at the interchange.

The weekend closures are scheduled to begin at 9 p.m. on Friday, January 26 and are expected to be completed by 5 a.m. on Monday, January 29, weather permitting. Closures at the interchange will include:

  • I-10 eastbound/westbound mainlanes from UTSA Blvd. to La Cantera Parkway
  • Loop 1604 eastbound/westbound mainlanes from Vance Jackson Rd. to La Cantera Parkway
  • Loop 1604 eastbound/westbound frontage roads between the I-10 eastbound and westbound frontage roads
  • Vance Jackson Rd. northbound/southbound lanes at Loop 1604 (nightly only)

This is a full weekend closure and lanes are expected to remain closed for the full duration. Local law enforcement will direct traffic through intersections during this time.

The traveling public is encouraged to plan an alternate route and avoid the interchange, if possible. Detour information for traffic through the interchange is listed below.

  • I-10 Eastbound Mainlanes Detour
    Travelers on the I-10 EB mainlanes looking to continue through the Loop 1604 interchange will exit to the I-10 EB frontage road after La Cantera Parkway and follow the I-10 EB frontage road through the interchange. Travelers will re-enter the I-10 EB mainlanes at the first entrance ramp after the Loop 1604 interchange.
  • I-10 Westbound Mainlanes Detour
  • Travelers on the I-10 WB mainlanes looking to continue through the Loop 1604 interchange will exit to the I-10 WB frontage road after UTSA Boulevard and follow the I-10 WB frontage road through the interchange. Travelers will re-enter the I-10 WB mainlanes at the first entrance ramp after the Loop 1604 interchange.

 Loop 1604 Eastbound Mainlanes and Frontage Road Detour

  • Travelers on the Loop 1604 EB mainlanes looking to continue through the I-10 interchange will exit at the Vance Jackson Road exit ramp to enter the Loop 1604 EB frontage road. Travelers will follow the signs for I-10 EB and continue on the I-10 EB frontage road to the U-turn at UTSA Boulevard. Travelers will follow the I-10 WB frontage road back to the Loop 1604 EB frontage road, entering the Loop 1604 EB mainlanes at Vance Jackson Road.
  • Loop 1604 Westbound Mainlanes and Frontage Road Detour
  • Travelers on the Loop 1604 WB mainlanes looking to continue through the I-10 interchange will exit at the I-10 exit ramp to enter the Loop 1604 WB frontage road. Travelers will follow the signs for I-10 WB and continue on the I-10 WB frontage road to the U-turn at La Cantera Parkway. Travelers will follow the I-10 EB frontage road back to the Loop 1604 WB frontage road, entering the Loop 1604 WB mainlanes after Valero Way.

CPS Energy is working to improve the quality of aging overhead electrical lines on the northwest sector at the intersection of IH 10 Frontage Rd and Heuermann Rd.

  • The IH 10 project will involve removing and installing a new overhead primary line across IH 10 Frontage Road and Heuermann Road and requiring rolling traffic stops. The work will take place on Sunday, January 28, 2024, from 6:00 a.m. – 4:00 p.m., weather permitting.

 CPS Energy contractor crews will be working on the above project, which will cause two scheduled outages affecting two business customers who have been informed.

 OSO will provide traffic control on the East and West bound sides of IH10 resulting in nine rolling traffic stops lasting up to 15 minutes.